2023/03/06 |
|
PCN(Product Change Notice)
|
Additional approval request for PMDTM (SOD-128) production at China (Tianjin) factory.
Now: Production Factory (Assembly) : Japan, Malaysia After: Production Factory (Assembly) : Japan, Malaysia, China (Tianjin)
Planned first ship date:May 6, 2023 |
2023/03/11 |
|
PCN(Product Change Notice)
|
Additional approval request for PMDTM ã SOD-128ã production at China~(Tianjin) factory |
2023/04/18 |
|
PCN(Product Change Notice)
|
Additional approval request for PMDU(M) 〈SOD-123FL〉 production at China (Tianjin) factory
Planned first ship date:May 6, 2023
Revised P/N |
2023/04/18 |
|
PCN(Product Change Notice)
|
Additional approval request for PMDTM (SOD-128) production at China (Tianjin) factory. Now: Production Factory (Assembly) : Japan, Malaysia After: Production Factory (Assembly) : Japan, Malaysia, China (Tianjin) Planned first ship date:May 6, 2023
Revised P/N |
2023/07/17 |
|
PCN(Product Change Notice)
|
CHANGE NOTIFICATION of Production Factory (Assembly) |
2025/04/01 |
|
PCN(Product Change Notice)
|
Supplier Notice No.:4024001 Title: Application for change due to discontinuation of wafer coating (polyimide) (power diode)
Detailed description of change: Before/ Wafer coating : conventional polyimide After/ Wafer coating : new polyimide
Reason for change: The polyimide material used for wafer coating will be discontinued, and will be replaced by an alternative material for continued supply.
Anticipated impact on quality: It has been comfirmed that there is no difference in reliability.
Planned first ship date: April 1, 2025 |